Project Calendar
Phase 1: Building out TeamDynamix
Target Dates: 1/2/24 – 7/10/24
Configuring TeamDynamix
- Administrator training & core configurations: January – March
- Portal: Late March – Early June
- Knowledge Base: Early April – Go Live
- Service Catalog: Early April – Go Live
- Ticketing: Early April – Early June
- Change Management: Early April – Early June
- Chatbot: Early May – Early July
- Reporting: Mid May – Go Live
TeamDynamix Integrations
- LDAP and Grouper: Early April – Mid May
- User and group management
- CCI & CRC: Mid April – Late May
- Fixably, Safeware, and Lenovo for Computer Repair Center and CCI services
- Service Accounts: Mid April – Late May
- Creation and distribution of service accounts for select TDX API integrations
- Canonical Data Sources: Mid April – Late May
- Includes SPOTS, CBM, Chartfield strings, HR Officers, etc.
- xMatters: Mid May – Mid June
- ITS Service Status: June
ServiceNow Closeout
- Investigate ServiceNow data archive requirements & structure: May – Go Live
Training & Access
- Agent Training: Mid June – Go Live
- TeamDynamix Agent Early Access: 2-3 weeks before Go Live
- TeamDynamix Go Live: July 10, 2024
Phase 2: Closing out ServiceNow
Target Dates: 7/10/24 – 9/6/24
ServiceNow Closeout
- Configuring TeamDynamix Asset module (Phase 2)
- Closing out ServiceNow contract and use
- Creating ServiceNow data archive
TeamDynamix Continued Buildout
- Asset Management: Mid July – Late August
- Knowledge Base & Service Catalog: Continue to build items not addressed for Go Live
Training & Access
- Agent Training: On Demand
- ServiceNow Late Access: 2-3 weeks post TeamDynamix Go-Live
- Decommission ServiceNow: by 9/6/2024
Phase 3: Continued TeamDynamix Buildout
Target Dates: 9/6/24 – 12/15/24
- Project Portfolio Management: Mid September – December
- Additional TeamDynamix Configuration: TBD
- Additional TeamDynamix Integrations: TBD